Table 7-5 DRM requirements
Mode Port on the SUN2000 Requirements
DRM0 DI1 and GND of the COM
port
● When switches S0 and S9 are
switched on, the solar inverter
should be turned o.
● When switch S0 is switched
o, and switch S9 is switched
on, the solar inverter should
be grid-tied.
Procedure
Step 1 On the home page, choose Settings > Feature parameters.
Step 2 Set DRM to .
Figure 7-19 DRM
----End
SUN2000-(2KTL-6KTL)-L1
User Manual 7 Man-Machine Interaction
Issue 10 (2023-02-13) Copyright © Huawei Technologies Co., Ltd. 87