Procedure
Step 1 If a battery is connected, turn on the battery switch.
Step 2 Turn on the AC switch between the SUN2000 and the power grid.
Step 3 Turn on the DC switch (if any) between the PV strings and the SUN2000.
Step 4 Turn on the DC switch at the bottom of the SUN2000.
Step 5 Observe the LED indicators to check the operating status of the SUN2000.
NO TICE
Delivering an upgrade command to the SUN2000 may cause power grid
connection failure, which aects the energy yield.
Only professionals are allowed to set the grid parameters, protection
parameters, feature parameters, and power adjustment parameters of the
SUN2000s. If the power grid parameters, protection parameters, and feature
parameters are incorrectly set, the SUN2000s may not connect to the power
grid. If the power adjustment parameters are incorrectly set, the SUN2000s
may not connect to the power grid as required. In these cases, the energy yield
will be
aected.
----End
SUN2000-4.95KTL-JPL1
User Manual 6 System Commissioning
Issue 05 (2023-02-17) Copyright © Huawei Technologies Co., Ltd. 65

Other manuals for Huawei SUN2000-4.95KTL-JPL1

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei SUN2000-4.95KTL-JPL1 and is the answer not in the manual?

Huawei SUN2000-4.95KTL-JPL1 Specifications

General IconGeneral
BrandHuawei
ModelSUN2000-4.95KTL-JPL1
CategoryInverter
LanguageEnglish

Related product manuals