EasyManuals Logo

IMT 4004i User Manual

IMT 4004i
60 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #29 background imageLoading...
Page #29 background image
Oshkosh Corporation Classification: Unrestricted
27
In This Chapter
Electric Crane Start-up and Task Performance ........................ 27
IMT Electric Crane Controls ..................................................... 29
Crane Shut Down ..................................................................... 33
Operation in Poor Conditions.................................................... 33
Hand Signals ............................................................................ 34
Electric Crane Start-up and Task Performance
CAUTION
AVOID MO TOR DAMAGE! The DC electric
motor can overheat. Run for short periods to
avoid overheating. The maximum pump
working period depends on the pressure
required, but working periods should never
exceed 5 minutes followed by cool down to
ambient temperature. See the technical
specifications for pump performance charts
and operating intervals.
Prior to lifting a load:
1 Find the weight of the load.
2 Find the weight of any load handling devices.
3 Add the load and load handling device weights. The sum is the total weight of the load being
lifted.
4 Find the distance from the crane rotation centerline to the load centerline.
5 Find the distance from the crane rotation centerline to the centerline of where the load is to
be moved to.
6 The crane reach required is the larger of items 4 and 5 above.
7 Check crane capacity using this distance and the load weight.
C H A P T E R 3
Operation

Other manuals for IMT 4004i

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IMT 4004i and is the answer not in the manual?

IMT 4004i Specifications

General IconGeneral
BrandIMT
Model4004i
CategoryConstruction Equipment
LanguageEnglish

Related product manuals