M920 & M920W pH/Dual ORP Controller Owner’s Manual
II. Installaon
A. Setup(Installaonvideoavailableatipscontrollers.com)
1. Turn o all peripheral equipment such as heaters, chemical feeders,
and pumps.
2. Relieve pressure from the ltraon system.
B. Tools
1. Cordless drill
2. 1/4” NPT Tap
3. 7/16” drill bit
4. 1/4” or 3/8” drill bit for Temp Sensor (oponal)
5. Masonry drill bit and anchors, or other appropriate fasteners
6. 13/16” wrench or channel-lock pliers
C. Procedure
1. Locaon
a. Wall area with easy access
b. Within 8 feet of feeder
c. At least 10 feet from water edge
d. Close proximity to me clock
e. Within 6 feet of GFCI power source
2. Mounng
a. Controller and ow cell are factory-mounted to ABS board for
your convenience.
b. Securely mount ABS mounng board with M920 controller and
ow cell on wall (vercal installaon).
c. If applicable, securely aach the peristalc pumps to the
oponal larger ABS mounng board with the provided
hardware.
11