PROGRAM AND OPERATE - ONE STAGE PROGRAM (Figure1)
9
OPERATION
1 Turnthepowerswitchon
2 PressPROGRAMNUMBERUsetodisplaythedesiredprogramnumber(P1-P30)
3 PressENTER/REVIEWtoselectthedisplayedPROGRAMNUMBERSTAGE1andNIGHTTIME
(DELAYEDSTART)lightsturnonEntertosetthetimerequiredfortheprogramtobecompletedand
readytocast(1-99hrs)
4 PressENTER/REVIEWSTAGE1lightremainson,NIGHTTIME(DELAYSTART)lightturnsoffand
HEATRATElightturnsonEntertoselecttheheatraterequiredfrom1°F-30°F/min
(1
o
C-17
o
C/min)or"FULL"forthemaximumheatrate
5 PressENTER/REVIEWSTAGE1lightremainson,HEATRATElightturnsoffandTEMPlightturnson
Entertoselectthetemperaturerequireduptothemaximumof2012°F(1100°C)
6 PressENTER/REVIEWSTAGE1lightremainson,TEMPlightturnsoffandHOLDTIMElightturnson
Entertoprogramthetimeneededtoholdatabovetemperature(0-4hrs)
7 Foronestage,thefurnacemustbeprogrammednottouseSTAGE2,3or4Followthesesteps:
AAftercompletingstep6,pressENTER/REVIEWSTAGE1lightturnsoff,STAGE2andHEATRATE
lightsturnon
BPressMainDisplayshows"5,4,3,2,1,COOL,NO"Select"NO"to
programthefurnacenottouseSTAGE2,3or4
8 Allnecessaryinformationforthisprogramisnowentered
9 Toruntheprogramimmediately,pressSTART/STOP
10Todelaythestartoftheprogramtobereadytocastatthepre-settime(seeStep3),pressNIGHTTIME
(DELAYSTART)
NOTE : If NIGHT TIME (DELAY START) is pressed while a program is running, the time