5376000253 4-15
If vehicle to be towed is on
a slope, do not release the
brake until the tie-down
straps are installed. Observe
the wheels in the grid for any
slippage.
15. It is recommended that the
steering wheel be secured by
a steering wheel strap for any
tow.
16. Lift the vehicle high enough
to allow the tires to clear the
ground. Make sure that the grid
is not in contact with any engine
or body components.
17. Remove the tie-down straps
from tool boxes and attach
the tie-down straps. (See Tie-
Down Strap instructions).
18. With the straps in place, the
vehicle in neutral and the parking
brake released, you can move
the vehicle safely up, down, in
or out. All of these movements
are hydraulically controlled by
the hand controller.
19. Raise the vehicle into the nal
towing position observing the
far end for su󰀩cient ground
clearance. It is possible to
set the rear of a front lifted
vehicle completely onto the
ground, causing damage. Take
irregular roadsurfaces into
consideration. Observe the lift
function from the side and away
from both vehicles if possible.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Jerr-Dan MPL-NG and is the answer not in the manual?

Jerr-Dan MPL-NG Specifications

General IconGeneral
BrandJerr-Dan
ModelMPL-NG
CategoryConstruction Equipment
LanguageEnglish