Structural Requirements 3
Site Preparation 3-5
Access Requirements
• Ramps
When moved on its casters, the testhead will negotiate ramps with inclines up
to 12% before the leveling feet drag on the floor.
• Hallways and door
As a rough guide, if you have room to move a 1.25 m x 2.5 m (4 by 8-foot) sheet
of plywood, parallel to the floor, through hallways and doors, you will be able to
move the crated testhead. If you cannot move the testhead crate all the way,
remove it from its crate in a receiving area and push it on its casters to the
destination.