Installation with two transformers:
This installation requires:
o 1 CT on phase L1 of each transformer
o 1 general summation CT 5+5…/5 A
The value of the primary to be programmed in the controller should be the
sum of the primaries of each transformer
Installation with two transformers and coupling system:
This installation requires:
o 1 CT on the main phase L1 of each transformer
o 1 CT on the group phase L1 for each transformer
o 1 general summation CT 5+5…/5 A for each transformer
The value of the primary to be programmed in the controller should be the
value of the primary for the transformer to which it is connected