Commissioning 6
55
EDBCSXE040 EN 6.0
6 Commissioning
Check before switching on the power supply module for the first time:
ƒ The wiring for completeness, short−circuit, and earth fault
ƒ The power connection:
Mains connection via terminals L1, L2, L3 (X21)
Connection of the RFI filter / mains choke
Connection of the brake resistor (internal/external) via terminals BR0, BR1 (X22)
Polarity of the DC bus voltage supply via terminals +UG, −UG (X22)
ƒ The control connection (X6):
Connection of the 24 V supply, GND
Connection of temperature sensor contact of the external brake resistor or
connection of jumper when using the internal brake resistor to terminals T1, T2.
Adjustment of wiring to the signal assignment of the control terminals.
ƒ The communication via the system bus (CAN)

Table of Contents