Inial switch-on
Operang instrucons I510-Cabinet
7 Commissioning
DANGER
Electrical voltage
Incorrect wiring can cause unexpected states during the commissioning phase.
Wiring must be complete and correct.
Check the wiring to ensure that it is free of short circuits and earth faults.
Adapt the motor circuit conguraon (star/delta) to the inverter.
Connect the motor in the correct phase relaon (rotang direcon).
Check the “Emergency o” funcon of the overall system.
Clear the hazard area.
Observe safety instrucons and safety clearances.
7.1 Keypad module
Plug the keypad onto the inverter.
The keypad can also be connected and removed during operaon.
6 Inialswitch-on
DANGER
Electrical voltage
Incorrect wiring can cause unexpected states during the commissioning phase.
Wiring must be complete and correct.
Check the wiring to ensure that it is free of short circuits and earth faults.
Adapt the motor circuit conguraon (star/delta) to the inverter.
Connect the motor in the correct phase relaon (rotang direcon).
Check the “Emergency o” funcon of the overall system.
Clear the hazard area.
Observe safety instrucons and safety clearances.
Condions
The power connecons must be wired.
The digital inputs X3/DI1 (start/stop), X3/DI3 (reversal of rotaon direcon) and
X3/DI4 (frequency preset 20 Hz) must be wired.
The analog input X3/AI1 must not be wired or connected to GND.
Switch on mains voltage
Switch on mains voltage and check readiness for operaon.
Observe LED status displays “RDY” and “ERR” on the inverter front panel.
See “LED status”.