3.6-1
300 mm
(12”)
3.6-2
3.6 Below deck preparation
IMPORTANT:
The positioning of the windlass must be checked prior to cutting for deck/hull and bulkhead clearance.
WARNING!
Failure to provide minimum vertical fall
will cause jamming.
1.The motor/gearbox is bolted via the through deck mounting bolts.
NOTE: Do not position motor/gearbox below rode/chain pipe fall area.
2. There must be sufficient vertical fall for the chain or rope when hauling in.