2-8
CDD3000-HF Operation Manual
2  Mechanical installation
2.5 Push-through 
heat sink (Dx.x)
 
 
Step Action Comment
1
Mark out the positions of the tapped 
holes and the breakthrough on the 
backing plate. 
Cut a tap for each fixing screw in the 
backing plate and cut out the 
breakthrough. 
Dimensional drawings/hole 
spacing see Table 2.5. 
The tapping area will provide you 
with good, full-area contact.
2
Mount the drive controller for high-speed 
drives vertically on the backing plate. 
Tighten all screws to the same tightness.
Pay attention to the mounting 
clearances! The mounting seal 
must contact flush on the surface.
3
Mount the other components, such as the 
mains filter, line choke etc., on the 
backing plate.
Mains filter max. 20 cm below the 
drive controller for highspeed 
drives
4
Continue with electrical installation in 
section 3.
Note the following points: 
• Distribution of power loss:  
• The all-round mounting collar must be fitted with a seal. The seal 
must fit flush on the surface and must not be damaged.
(1) Seal  
(2) Tapped hole for 
EMC contact
(3) Outside
(4) Inside
• The backing plate must be well grounded.
• The best result for effective EMC installation is attained with a 
chromated or galvanized backing plate. If backing plates are 
varnished, the coating must be removed in the area of the contact 
surface!
 
BG3 BG4 BG5
Power loss
Outside (3) 70% 75% 80%
Inside (4) 30% 25% 20%
Protection
Heat sink side (3) IP54 IP54 IP54
Machine side (4) IP20 IP20 IP20
(4)
(3)
X5
X6 X7
(1)
(2)