3.1. Lifting & Transporting
For safe movement of the Shear there are two Fork Lift Channels as shown below. Use
at all times when lifting the Shear and check the capacity of the equipment to be used.
Do not attempt to lift the Shear by any other means
The Shear is also on wheels, however for movement over longer distances or uneven
ground lifting the Shear with a forklift is advisable.
3.2. Siting & Installation
The Shear must be sited on level ground, ideally on sound concrete, and in good ambient
lighting. The Shear must not be allowed to rock back and forth while in operation. Site the
Shear in a position which will allow the Operator to walk freely and unhindered around all
sides. Ensure that the working area around the Shear is kept clear of metal and debris.
The Shear should be sited such that the noise generated is not reverberated or amplified
by the surroundings and does not disturb other Workstations or Operators.
Sound Pressure Level above 70 dBA
Fork Lift Channels