Power feedback protection
Firmware version inconsistent
Battery voltage detected different
AC input voltage and frequency detected different
AC output current unbalance
AC output mode setting is different
Unidentified unit master or slave
7. Commissioning
Parallel in single phase
Step 1: Check the following requirements before commissioning:
Correct wire connection
Ensure all breakers in Line wires of load side are open and each Neutral wires of each unit are
connected together.
Step 2: Turn on each unit and set “PAL” in LCD setting program 28 of each unit. And then shut down all
units.
NOET: It’s necessary to turn off switch when setting LCD program. Otherwise, the setting cannot be
programmed.
Step 3: Turn on each unit.
LCD display in Master unit
LCD display in Slave unit
NOTE: Master and slave units are randomly defined.
Step 4: Switch on all AC breakers of Line wires in AC input. It’s better to have all inverters connect to utility at