Install the IntrCooll®
Version 1.3, 2021-12-14 51
1
2
3
4
5
C Thermostat connected with correct cable, to specied connection
in IntrCooll®?
o o
Thermostat control on page 37
D If Oxyconnect gateway is ordered, are necessary preparations
done?
o o
Oxyconnect gateway
control on page 38
E If Building Management System will control the unit, is contractor
informed to take care of installation?
o o
Control by a Building
Management
System on page 39
F IntrCooll® used as AHU pre-cooling, is unit connected to specied
instructions?
o o
Control by an air handling
unit on page 39
Remarks:
6 Water Supply requirements YES NO
A Local water quality according to specication?
o o
Supply water quality
requirements
B Measured and noted the conductivity of the water on the site?
o o
Supply water quality
requirements
C Water Supply according to specications?
o o
Supply connections
D Shut- o valve provided and installed by contractor?
o o
Valves on page 36
E Maintenance water connection/valve provided and installed by
contractor?
o o
Valves on page 36
F Prepare piping for drain and overow connection.
o o
Drain connections on page 35
Overow
connections on page 35
G Drain valve installed according instructions?
o o
Step 4. Drain valve installation