en
14
Installation Commissioning Settings AccessoriesTroubleshooting
Display
Commissioning menu
4. Date
Î Adjust the date.
Current date
Adjustment range:
01.01.2001... 31.12.2099
5. System
Î Adjust the desired system scheme
for the system
For a detailed description of the system
schemes to choose from, see chap. 2.
If the system layout selection is changed
later on, any previous adjustments
which have been made in the other
channels will be lost.
System selection
Adjustment range: 1 ... 8
Factory setting: 1
6. Minimum temperature of the
solid fuel boiler
Î Adjust the desired minimum tem-
perature of the solid fuel boiler
Tmin SFB / boiler
Minimum temperature of the solid fuel
boiler
Adjustment range: 10 ... 80 °C
Factory setting: 60 °C
7. Switch-on temperature differ-
ence SFB / boiler
Î Adjust the desired switch-on
temperature difference
∆Ton SFB / boiler
Switch-on temperature difference solid
fuel boiler
Adjustment range: 1.0 ... 25.0 K
Factory setting: 6.0 K
Note:
The switch-on temperature
difference must be at least
0.5 K higher than the switch-
off temperature difference. The
adjustment range will automat-
ically adapt to that.
8. Switch-off temperature difference
Î Adjust the desired switch-off
temperature difference
∆Toff SFB / boiler
Switch-off temperature difference solid
fuel boiler
Adjustment range: 0.5 ... 24.5 K
Factory setting: 4.0 K
Note:
The switch-off temperature
difference must be at least
0.5 K lower than the switch-on
temperature difference. The
adjustment range will automat-
ically adapt to that.