5 Commissioning
5.1 Tests before the initial commissioning
mechanical functional check
►
Chec
k whether the switch is correctly actuated and remains in the OFF position by
pulling the rope at all positions and in all directions.
►
Check that the rope is unimpeded.
electrical functional check
►
Set blue reset lever to “1” position.
►
Start the machine.
►
Check whether the machine stops when the rope is pulled.
►
Switch off the machine.
►
Actuate the rope pull switch.
►
The machine is not allowed to start if the rope pull switch has been actuated.
5.2 Periodic technical inspections
To ensure correct function over the long term, regular checks are necessary.
WARNING
Pr
ior to resetting the machine after each time the rope pull switch is actuated, the
reason for triggering the switch must be checked along the entire length of the rope.
Daily or prior to the start of the shift the operator must check for:
►
c
orrect function
►
Machine stops when pulling on the rope.
►
no visible evidence of tampering
Regularly according to the machine maintenance schedule by the competent person‐
nel
►
correct switching function
►
safe assembly of the modules
►
deposits and wear and tear
►
correct sealing of the cable entry or plug connection
►
loose cable connections or plug connectors
WARNING
T
he entire switch must be replaced in the case of damage or wear and tear.
It is not permitted to exchange individual components or modules.
Rope pull switches must be completely replaced after 1 million switching operations.
5.3 Disposal
Procedure
►
Al
ways dispose of unusable devices in accordance with national waste disposal
regulations.