EasyManuals Logo

Siemens 3AP2-FI User Manual

Siemens 3AP2-FI
109 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #76 background imageLoading...
Page #76 background image
75
4 Installation
4.9 Checks before Commissioning
Attention
The items listed below should be strictly followed during commissioning.
4.9.1 Anti-Condensation Heaters
Check that heating resistors in the three operating mechanism cubicles and in the control cubicle are working,
and also the function of any monitoring equipment fitted.
4.9.2 Test of Wiring between Substation and Circuit-Breaker
Check all command and signalling paths.
4.9.3 Commissioning Report
It should be checked that the commissioning report enclosed with the circuit-breaker has been completed in full
and signed.
Please return it to the manufacturer at the following address:
Siemens Ltd.
PTD-Division
E-76. Waluj MIDC
Aurangabad 431136

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens 3AP2-FI and is the answer not in the manual?

Siemens 3AP2-FI Specifications

General IconGeneral
BrandSiemens
Model3AP2-FI
CategoryCircuit breakers
LanguageEnglish

Related product manuals