4 Installation
4.9 Checks before Commissioning
Attention
The items listed below should be strictly followed during commissioning.
4.9.1 Anti-Condensation Heaters
Check that heating resistors in the three operating mechanism cubicles and in the control cubicle are working,
and also the function of any monitoring equipment fitted.
4.9.2 Test of Wiring between Substation and Circuit-Breaker
Check all command and signalling paths.
4.9.3 Commissioning Report
It should be checked that the commissioning report enclosed with the circuit-breaker has been completed in full
and signed.
Please return it to the manufacturer at the following address: