05.00  Transport, Unpacking and Assembly 
Siemens AG    6SE7087-6AK85-1AA0 
2-1 
Rectifier/Regenerating Unit    Operating Instructions 
2  Transport, Unpacking and Assembly 
2.1  Transport and unpacking 
The units are packed at the manufacturing works. A product packaging label is attached to the box. 
Avoid extreme vibrations and hard impacts during transport, e.g. when lowering the unit. 
Pay attention to the notes on the packaging relating to transport, storage and proper handling. 
The converter can be installed after unpacking it and checking the consignment for completeness and 
damage. 
The packaging consists of cardboard and corrugated cardboard for units of size C. The units of size E, H 
and K are bolted onto pallets with fixing pieces in their usual operating position and packed with 
cardboard. The packaging may be disposed of in accordance with local cardboard disposal regulations. 
You should notify your freight forwarder immediately if you discover any transportation damage. 
 
2.2 Storage 
The units must be stored in clean dry rooms. Temperatures between −25 °C (−13 °F) and + 70 °C (158 °F) are 
permissible. Temperature fluctuations > 20 K per hour are not permissible. 
 
2.3 Assembly 
The following are required for securing size C: 
♦  G rail conforming to EN50035 with screws for securing 
♦  one M6 bolt 
♦  dimension drawing (Figure 2.2 for size C)  
 
The following are required for securing size E: 
♦  four M8 bolts 
♦  dimension drawing (Figure 2.3 for size E) 
 
The following are required for securing size H: 
♦  four M8 bolts 
♦  dimension drawing (Figure 2.4 for size H) 
 
The following are required for securing size K: 
♦  six M8 bolts 
♦  dimension drawing (Figure 2.5 for size K) 
 