7SR242 Duobias Commissioning & Maintenance Guide 
©2010 Siemens Protection Devices Limited     Chapter 6 Page 6 of 57 
1.2.3 Test Equipment 
Required test equipment is: 
Secondary injection equipment with integral time interval meter 
Primary injection equipment 
A d.c. supply with nominal voltage within the working range of the relay's d.c. auxiliary supply rating 
A d.c. supply with nominal voltage within the working range of the relay’s d.c. binary input rating 
Other equipment as appropriate to the protection being commissioned – this will be specified in the product 
specific documentation. 
The secondary injection equipment should be appropriate to the protection functions to be tested. Additional 
equipment for general tests and for testing the communications channel is: 
•  Portable PC with appropriate interface equipment. 
•  Printer to operate from the above PC (Optional). 
 
Use of PC to facilitate testing 
The functions of ReyDisp Evolution (see Section 2: Settings and Instruments) can be used during the 
commissioning tests to assist with test procedures or to provide documentation recording the test and test 
parameters. One method is to clear both the waveform and event records before each test is started, then, after 
the test upload from the relay the settings, events and waveform files generated as a result of application of the 
test. These can then be saved off to retain a comprehensive record of that test. 
Relay settings files can be prepared on the PC (offline) or on the relay before testing commences. These settings 
should be saved for reference and compared with the settings at the end of testing to check that errors have not 
been introduced during testing and that any temporary changes to settings to suit the test process are returned to 
the required service state. 
A copy of the Relay Settings as a Rich Text Format (.rtf) file suitable for printing or for record purposes can be 
produced from ReyDisp as follows. From the File  menu select Save As, change the file type to Export 
Default/Actual Setting (.RTF) and input a suitable filename.  
When testing is completed the event and waveform records should be cleared and the settings file checked to 
ensure that the required in-service settings are being applied.  
 
1.2.4 Precautions 
Before electrical testing commences the equipment should be isolated from the current and voltage transformers. 
The current transformers should be short-circuited in line with the local site procedure. The tripping and alarm 
circuits should also be isolated where practical. The provision and use of secondary injection test sockets on the 
panel simplifies the isolation and test procedure. 
Ensure that the correct auxiliary supply voltage and polarity is applied. See the relevant scheme diagrams for the 
relay connections.  
Check that the nominal secondary current rating of the current and voltage transformers has been correctly set in 
the System Config menu of the relay.