SD39RIO-1 INSTALLATION
January 2001
2-3
In a non-redundant or module-to-module redundant APACS+ system, when IOBUS cable length
needs are longer than the maximum standard cable 98.4 ft (30 m), an unterminated two-
conductor shielded cable can be spliced into a standard IOBUS cable
In a rack-to-rack redundant or any QUADLOG system, when IOBUS cable length needs are
longer than the maximum standard cable 98.4 ft. (30 m), an unterminated six-conductor shielded
cable can be spliced into a standard IOBUS cable
2. Determine the number of racks to be installed. The Remote I/O Rack is intended for flush mounting on a
flat surface such as an instrument panel or wall.
3. If required, up to four Remote I/O Racks (marshalled I/O terminations only) can be installed in a
MODLUPAC enclosure if one or more flat panels are installed in the enclosure first. If an enclosure is
user-supplied, refer to Figure 2-2 for Remote I/O Rack dimensions and determine the desired enclosure
layout.
4. Prepare or amend system drawings to document:
The physical location of Remote I/O Rack(s), plug-in I/O modules, and other related items such as
power supplies and marshalled termination assemblies
Identify the routing of all associated cables and power wiring (e.g. DC power, twinaxial
communications cable, IOBUS, and MODULBUS). Do not assign IOBUS cables to conduits
containing telephone lines
The position of each backplane IOBUS Shunt (refer to section 2.5.6 for IOBUS Shunt information)
Each Remote I/O Rack’s intended rack address and slot switch setting
5. Install needed cable raceways and conduits.
6. Install Remote I/O Racks and associated marshalled termination assemblies at their intended installation
sites. Where applicable, identify cable entrances in cabinets. Tag and route IOBUS extension cables;
pull them into the cabinets.
7. For each Remote I/O Rack, set its rack address switch and slot address range switch according to system
drawings.
8. Key and install I/O modules in the Remote I/O Rack(s). For detailed installation instructions, refer to the
information in this document and the documentation for each I/O module.