INSTALLATION SD39RIO-1
January 2001
2-40
2.12 I/O Cable Installation
Each I/O module to be installed in the Remote I/O Rack is to connect to its I/O field wiring via an
Interconnect I/O Cable Assembly. Each cable extends from a module slot position in the Remote I/O Rack to
a companion marshalled termination assembly that provides I/O field terminals. The Remote I/O Rack can
accommodate up to four cable assemblies. Installation of these cable assemblies, as shown in Figure 2-30, is
commonly performed at the time of rack installation (prior to module installation).
Figure 2-30 Installing Module End of I/O Interconnect Cable