7KT multimeter
Manual, 08/2018, 2514284149-01
49
Commissioning
6
6.1
Overview
Prerequisites
The device has been installed.
The device has been connected in accordance with the possible connection methods.
Steps for starting up the device
NOTICE
Risk of malfunction or device failure!
Incorrect connection can result in malfunctions and failure of the device.
Before connecting the device, ensure that the local power supply conditions match the
specifications on the type plate.
Before starting up the device, check that all connections are correct.
Note
Before performing an insulation test of
the entire installation with AC or DC, you must
disconnect the device from the line voltage.
1. Apply the measuring voltage. You can find more information on this in chapter
Connecting (Page 41).
2. Parameterize the device. You can find more information on this in chapter Parameterizing
with powerconfig (Page 50).
3. Check the measured values.