5.2 Preconditions
Only carry out the commissioning if the following requirements have been fulfilled:
The technical specifications for the hardware layout have been adhered to, see
Chapter:
Technical requirements
(Page 23).
The DRIVE-CLiQ connections are implemented in accordance with the system requirement
between the Motor Modules Booksize connected in parallel and the following components:
Encoder modules, any existing DRIVE-CLiQ encoders
Control Unit CU320-2 with CF card, Firmware V5.2
Note
Commissioning of the parallel connection
Remove other Motor Modules from the DRIVE-CLiQ group before commissioning the
parallel connection.
Always create the project for the Motor Modules Booksize connected in parallel first.
The supply voltage is connected.
The STARTER commissioning tool is started on the commissioning PC/PG.
The connection between the Control Unit and the commissioning PC/PG is established.
Commissioning
5.2 Preconditions
Motor Modules Booksize parallel connection
34 Application Manual, 01/2020, 6SL3097-5BF00-0BP0