19 Parameter Lists SMA Solar Technology America LLC
180 SI4548-6048-US-BE-en-21 Operating Manual
07 ChpPwrEna Activate CHP plant
request based on
power
Disable Disable Enable
Enable Enable
08 ChpPwrStr CHP plant request,
connection power limit
4 kW
09 ChpPwrStrDly Time delay for power
request for CHP plant
5 min
10 ChpManStr Manual CHP start Auto Automatic Auto
Start Starting
Stop Stopping
11 ChpAddOnTm Time activated for the
additional CHP plant
request
60 sec
12 ChpAddOffTm Time deactivated for
the additional CHP
plant request
120 sec
13 ChpAddSocDel Distance to the next
SOC limit
5%