6 Electrical Connection
SMA Solar Technology AG
Operating manualSTP50-40-BE-en-1534
Residual-current monitoring unit:
The inverter does not require an external residual-current device when operating. If local
regulations require the use of a residual-current device, the following must be observed:
The inverter is compatible with type B residual-current devices that have a rated residual
current of 300mA or higher (information about the selection of a residual-current device see
technical information "Criteria for Selecting a Residual-Current Device" at www.SMA-
Solar.com). Each inverter in the system must be connected to the utility grid via a separate
residual-current device.
When using residual-current devices with a rated residual current < 500mA, the rated residual
current must be set in the inverter (see Section8.20, page75). In this way the inverter
reduces the operational leakage currents and prevents a false triggering of the residual-current
device.
Overvoltage category:
The inverter can be used in grids of overvoltage categoryIII or lower in accordance with
IEC60664-1. That means that the inverter can be permanently connected to the grid-connection
point of a building. In case of installations with long outdoor cabling routes, additional measures to
reduce overvoltage categoryIV to overvoltage categoryIII are required (see the Technical
Information "Overvoltage Protection" at www.SMA-Solar.com).
6.2.2 Connecting the Inverter to the Utility Grid
Requirements:
The connection requirements of the grid operator must be met.
The grid voltage must be within the permissible range. The exact operating range of the
inverter is specified in the operating parameters.
Procedure:
1. Disconnect the circuit breaker from all three line conductors and secure against reconnection.
2. Ensure that the DC load-break switch is in the O position and is secured against reconnection.
3. If the enclosure lid of the AC Connection Unit is
mounted, remove all ten screws of the enclosure lid
using a Torx screwdriver (TX25) and remove the
enclosure lid towards the front.
10x
4. Remove the adhesive tape from the enclosure opening for the AC connection.