8 Operation
SMA Solar Technology AG
Operating manualSTP50-40-BE-en-1566
8.7 Starting the Installation Assistant
The installation assistant leads you step-by-step through the steps necessary for the initial
configuration of the inverter.
Layout of the installation assistant
A
C
B
Figure 17: Layout of the installation assistant (example)
Position Designation Description
A Configuration steps Overview of the installation assistant steps. The number of
steps depends on the type of device and the additionally
installed modules. The current step is highlighted in blue.
B User information Information about the current configuration step and the
setting options of the configuration step.
C Configuration field You can make settings in this field.
Requirement:
When configuring after completion of the first tenfeed-in hours or after exiting the installation
assistant, the SMA Grid Guard code must be available in order to change the grid-relevant
parameters (see "Application for SMAGridGuard Code" at www.SMA-Solar.com).
Procedure:
1. Open the user interface (see Section8.2, page56).
2. Log in as Installer.
3. Select the menu User Settings (see Section8.4, page62) on the start page of the user
interface.
4. In the context menu, select [Starting the installation assistant].
The installation assistant will open.