80-136KTL User manual
Copyright © Shenzhen SOFARSOLAR Co., Ltd
Procedure:
6.Commissioning of inverter
Outlines this Chapter
Introduce SOFAR 80-136KTL safety inspection and start processing
6.1. Cable Connection Inspection
For first time operation, check the AC voltage and DC voltage
are within the acceptable range
AC grid connection
Use multimeter to confirm that three lines and PE line are connect correctly. DC pv
connection