11. ClosetheConnectionUnitexternalcover:Attachthecoverandsecureitbytighteningthesixscrews
withatorqueof1.2N*m/0.9ft.*lb.
12. Ensureproperconduitsealing;inspecttheentireconduitrunandusestandardconduitsealantsto
avoidwaterpenetration.
13.
TurnONtheConnectionUnitswitch.IfanadditionalexternalDCswitchisinstalledbetweenthe
poweroptimizers/batteryandtheinverter(s)thenturnitON.
AstatusscreensimilartothefollowingappearsontheLCDpanel:
V a c [ V ] V d c [ V ] P a c [ w ]
2 4 0 . 7 1 4 . 1 0 . 0
P _ O K : 0 0 0 / 0 0 0 < S _ O K >
- - - - - - - - - - - - - - - O F F
14. VerifythatthefollowinginformationappearsontheLCDpanel:
l P_OK:Appearsonlyuponpairingprocesscompletionandfirsttelemetryreceptionfromthe
poweroptimizers.Indicatesconnectiontothepoweroptimizersandthatatleastonepower
optimizerissendingmonitoringdata.
l 000/000:Appearsonlyuponfirsttelemetryreceptionfromthepoweroptimizers.Indicatesthe
numberofpoweroptimizersthathavebeenpairedtothisinverter.
l S_OK:TheconnectiontotheSolarEdgemonitoringplatformissuccessful(shouldappearonlyif
theinverterisconnectedtotheserver).
l Vac [V]:ThegridACoutputvoltage.Verifythecorrectvalue.
l Vdc [V]:TheDCinputvoltageofthelongeststringconnectedtotheinverter.Thereshouldbea
safetyvoltageof1Vforeachpoweroptimizerinthestring.
NOTE
A measurement error on the inverter LCD of ±3 V is acceptable.
l Pac [w]:TheACoutputpower(shouldbe0.0sincetheinverterisOFF).
l OFF:TheinverterON/OFFswitchisintheOFFposition.
SolarEdge-StorEdge Installation Guide MAN-01-00262-1.3
48
Step 1: Activating the System