Off-site Planning, Prior to Visit
Below you will find at list of questions and considerations to take into account during the planning
phase prior to visiting a site.
If Customer Wants to Replace Existing IP-DECT/DECT
System
Is it an IP-DECT base station or a digital DECT base station?
l IP-DECT base station:
o
Consider PoE, Active equipment, Switch PoE.
o
Is this reusable for the new system?
o
Do LAN switches support LAN synchronization?
l Digital DECT base station:
o
Can the cabling be reused? (yes/no/partly)
Investigate:
o
Is all cabling twisted pair end to end (recommended equal to CAT5e)? Is cabling
present where DECT coverage is needed?
o
Are all junction points of good quality?
o
From these investigations the costs to get cabling up to a satisfactory standard can be
estimated.
Note:
Today new systems can be a combination of wired and IP.
Investigate Site
l What is the site?
o
Are there more buildings?
o
If there are more buildings - consider the distance between the buildings, and whether it
is possible to establish synchronization between base stations.
o
Are there more sites (sub-sites)?
o
If there are several sites - the remote site(s) (i.e. those where it will not be possible to
establish synchronization) must be IP-DECT/DECT system(s).
l Study blueprints of building
Spectralink IP-DECT Server 400/6500 and DECT Server 2500/8000 Synchronization and Deployment Guide