handset for deployment, see Site Survey Function in Handset User Guide.
Note:
It is important to measure all places where coverage is required.
Do not assume that there is coverage - it has to be measured!
l Note how far the place is from the tripod with the Spectralink IP-DECT Server 400.
l Find the next place for the base station app 2 x the above distance from the first placement
l Consider where to place the next base so that the handset gets opportunity to handover to the
next base station.
l Move your tripod with the Spectralink DECT Server 400/2500. and measure whether this will
give sufficient overlay (i.e. RSSI value min 70, Q value stays constant at 64 and good sound
quality) at the same place as measured at the previous placement.
l If necessary, move the base station to get sufficient overlay.
l When it is determined where to place the next base stations.
Note:
Take picture of the placement and note it on a blueprint of the building.
l Continue until the whole site is deployed.
Note:
Remember to document each placement for base stations (incl. sync master).
o
Take pictures of where exactly the base station must be placed.
o
Note it on a drawing of the premises.
Spectralink IP-DECT Server 400/6500 and DECT Server 2500/8000 Synchronization and Deployment Guide