Section 5
SEQUENCING TIMERS
18
3 Stopped
If the system pressure drops below the Sequence Load pressure (102) but is above the
Lowest Pressure (70), the next machine in sequence (2) will start and trim, and the previ-
ously trimming machine (1) will go to full load after the Delay Start timer expires. If the pres-
sure is at 85 then the machine will start in about 1 minute (see previous table).
Machine
S
tatus
1 Full Load
2 Trim
3 Stopped (Next machine in sequence)
If the system pressure stays below the Sequence Load pressure then the next machine in
sequence (3) will start after the Delay Start timer expires. If the pressure is at 85 then the
machine will start in about 1 minute (see table above).
Machine
Status
1 Full Load
2 Full Load
3 Trim