4.4 Installation Clearance Requirements
Reserve enough clearance around the battery to ensure sufficient space for heat
dissipation.
In case of multiple batteries, reserve specific clearance between the batteries.
The distance is only the recommended distance, which can be adjusted accord-
ing to the actual situation.
4.5 Installation Tools
Installation tools include but are not limited to the following recommended ones. If necessary,
use other auxiliary tools on site.
User Manual 4 Mounting

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Sungrow SBR064 and is the answer not in the manual?

Sungrow SBR064 Specifications

General IconGeneral
Battery TypeLithium Iron Phosphate (LFP)
Nominal Voltage51.2 V
Battery Module Energy6.4 kWh
Operating Temperature-10°C to 50°C
CommunicationCAN/RS485
Protection LevelIP65
ScalabilityUp to 8 modules in parallel
Cycle Life6000 cycles @ 80% DoD