TB9100/P25 CG/P25 TAG Installation and Operation Manual Appendix B – Inter-Module Connections 145
© Tait Limited March 2014
Special care should be taken when connecting the power cable from the
PMU to PA 2. The cable should be shaped in such a way that it does not
come into contact with the subrack interconnect board. Refer to the
diagram below for more detail.
Detail of cabling from PMU to PA 2