114-94438 REV C1
6.6. End of Line Test
The assembled Charge Inlet has to be tested electrically and mechanically to applicable
requirements,
including High Voltage test.
As a minimum the following tests have to be performed:
- Isolation resistance:
TEST VOLTAGE: 1000VDC
Inspection Duration: 1s
min. Riso: 200MOhm
AC versus AC; AC versus multicore shield, DC+ versus DC-; DC versus DC shield
- Dielectric withstand voltage:
TEST VOLTAGE: 1500VAC
Inspection duration: 1s
max. leakage current: 10mA
AC versus AC; AC versus multicore shield, DC+ versus DC-; DC versus DC shield
- Correct pinning
- Check seals for correct seating / Check of leakage
- Gauge check of geometrical interface acc. IEC 62196-3
- Functionality of connector locking device (mechanical check of pin movement in locking and
unlocking position)