Section 3 - Step-By-Step Assembly
Temp-Cast 2000 Installation Manual
11
STEP 1: "THERMOTECT" INSULATING BOARD
If an optional insulating board is to be installed, it is installed before starting the Levelling Pad.
Cut the board to size as indicated and place it in position. Check that it is square to the concrete
floor pad. Ensure that the air intake hole is located immediately in front of the board and centered.
(It is also advisable at this point to double check that there will be sufficient clearances to
combustible construction around the fireplace.)
If you have followed the Temp-Cast Planning Guide, the area around the 6" diameter Ash Drop
hole in the concrete pad will be sloped towards the hole for a few inches all around. Cut an
appropriately sized hole in the insulating board so that the sloped area around the hole is not
obstructed. Lay the board in position as illustrated.