11. Reverse conveyor by moving hydraulic selector valve outward. This will reverse the lower
conveyor and incline conveyor.
12. Verify pressure at each gauge.
a. Pressure at lower conveyor return line which now is the pressure line should read
between 500 to 1000 psi.
b. Pressure on incline conveyor pressure line should read 0 psi.
13. Check rear incline conveyor to verify that the conveyor did not drift down during testing.
If the incline conveyor drifts down check for air in cylinder lines. If conveyor continues to drifts
down then replace check valve cartridge and repeat steps 5 and 11 to verify the conveyor does
not drift down.
14. Testing is complete. Power down hydraulic power unit.
15. Remove all test gauge equipment by reversing the installation instructions and insure all ttings
are tight.
16. Restart power unit and operate conveyor system in both forward and reverse direction to
remove any air that might have gotten into the system.
17. Lower rear incline conveyor into stowed position.
18. Inspect all ttings and valves for leaks. Tighten as required.
19. Power down hydraulic power unit and remove Flow Meter Assembly.