5
INTRODUCTION TO PROGRAMMING WATERING SCHEDULES
When programming the controller, there are the 
following to consider:
STATIONS OR ZONES
your controller has either six (6) or eleven (11) 
Stations, depending on the model. Each Station 
has a group of sprinklers in a specific portion 
(Zone) of the garden and is controlled by a 
solenoid Valve. Zones are generally laid out 
according to the type of plant material being 
watered and the type and flow rate of the 
sprinklers used to distribute the water.
PROGRAMS
up to six (6) watering Programs can be set and 
applied to any of the Stations. For each Program, 
the following are programmable:
• Watering Days
 watering may be programmed to occur on
       - fixed days of the week
 (eg. Mon, Wed and Fri),
       - at intervals of a number of days
 (eg. every third day), or
       - on odd or even days of the month
          (eg. 1st, 3rd, 5th, 7th etc.)
• Start Time
 each program may have up to six (6)
 Start Times
• Run Time 
 each Station (or Zone) has an associated
   Run Time
Programming is a lot easier if you first fill out a 
Watering Schedule Form, an example of which is 
on the next page. You will have a record of your 
watering schedule and zone locations which can 
be kept with your controller. In the
example, four Programs have been
programmed:
• Program 1 starts at 7:00am on Mondays and 
   Thursdays and runs for 20 minutes on
   Stations 1, 2, 3, 5 and 6
• Program 2 starts at 9:00pm every day and 
   runs for 10 minutes on Stations 3 and 6. Note 
   that if no Watering Days are programmed, 
   the Lawn Dial Controller defaults to every day
• Program 3 starts at 6:00am every third day 
   and runs for 10 minutes on Station 4 only
• Program 4 starts at 5:00am on Tuesdays and 
   Sundays and runs for 30 minutes on Station 
   6 only.
Note: The Controller runs all programmed
watering sequentially, with only one Valve open 
at any given time. In the example, Program 1 will 
water Station 1, then Station 2, then Station 3, 
then Station 5 and then Station 6, beginning at 
7:00am, and taking a total time of 100 minutes.
If another Program was scheduled to start at say 
8:00am, it would be delayed until 8:40am (the 
completion of Program 1).
Therefore, when scheduling multiple programs
and/or multiple start times within each
program, make sure that each program cycle 
can run to completion before the next program 
cycle is scheduled to start. If you do not do this, 
the Controller will automatically stack them in 
sequence.