Pre-Installation
16 RTHD-SVX01K-EN
Installation Requirements
A list of the contractor responsibilities typically associated
with the unit installation process is provided in Table 4.
Table 4. Installation requirements
Requirement
Trane Supplied,
Trane Installed
Trane Supplied,
Field Installed
Field Supplied,
Field Installed
Rigging
•Safety chains
• Clevis connectors - Lifting beam
Disassembly/
Reassembly
(as required)
(a)
• Trane, or an agent
of Trane specifically authorized to
perform start-up of Trane
®
products
(contact
your local Trane
office for pricing)
Isolation
• Isolation pads • Isolation pads
Electrical
• Circuit breakers or non-fused
disconnects (optional)
• Unit-mounted starter
• Circuit breaker or non-fused disconnect
handle
• Temperature sensor (optional outdoor
air)
• Flow switches (may be field-supplied)
• Condenser water regulating valve
controller (optional: may be field-
supplied)
• Circuit breakers or fusible disconnects
(optional)
•Terminal lugs
• Ground connection(s)
• Jumper bars
• BAS wiring (optional)
•IPC wiring
• Control voltage wiring
• High condenser pressure interlock wiring
• Chilled water pump contactor and wiring
• Condenser water pump contactor and
wiring
• Optional relays and wiring
Water piping
• Flow switches (may be field-supplied)
• Condenser water regulating valve
controller
(optional- may be field-supplied)
• Thermometers
• Water flow pressure gauges
• Isolation and balancing valves in water
piping
• Vents and drain valves
• Pressure relief valves
(for water boxes as required)
Pressure Relief
• Relief valves
Vent line and flexible connector
Insulation
• Insulation (optional)
Insulation
Optimus™ RTHD
Installation
Completion Check
Sheet and Request
for Trane Service
(RLC-ADF005*-EN,
see “Log and Check
Sheets,” p. 87)
Chiller Start-up
Commissioning
(b)
• Trane, or an agent of
Trane specifically authorized to
perform start-up of Trane
®
products
(a)Trane, or an agent of Trane specifically authorized to perform start-up and warranty of Trane
®
products, will perform or have direct on-site supervision
of the disassembly and reassembly work.
(b)Start-up must be performed by Trane or an agent of Trane specifically authorized to perform start-up and warranty of Trane
®
products. Contractor shall
provide Trane (or an agent of Trane specifically authorized to perform start-up) with notice of the scheduled start-up at least two weeks prior to the
scheduled start-up.