74 ARTC-SVX005A-EN
Appendix B- Request for Initial Startup
PolyTherm Chiller/Heater
As part of a continuous commitment to quality, initial startup of this chiller/heater by a factory certified technician may
be purchased from Trane. No initial startup will be scheduled without a Request for Initial Startup form completed and
on file with the Trane customer service department. Submitting this form indicates that all critical work described on the
form has been completed. To prevent additional charges for aborted startups, the following items must be completely
functional and operating and this form signed and returned to Trane at least 10 working days prior to the scheduled initial
startup date.
Chiller/Heater Initial Start-up Data
Model Number: Master Module Serial Number:
Primary Contact Name: Primary Contact Phone:
Primary Contact FAX: Primary Contact Mobile:
Name of Chiller Site:
Physical Location of Chiller:
Requested Date for Initial Start-up:
Requested Time for Initial Start-up:
Mandatory Initial Startup Requirements
Mandatory Tasks
Date
Completed
Initialed
Complete
All modules are installed with minimum clearances exceeded on all sides.
Refrigeration gauges are indicating equal pressures.
Chilled water lines from chiller to customer’s equipment are permanently connected.
Chilled water lines have been flushed clean of mud, slag, and other construction debris.
All chilled water line filters and strainers are clean.
Chilled water lines have been leak tested according to prestart instructions.
Chiller reservoir (if included) is at operating level with correct water/glycol mixture.
High voltage wiring is installed, tested, and functional.
All water, refrigeration, electrical, and control connections between chiller modules are
completed.
All control wiring between modular chillers is installed, tested, and functional.
Control wiring is complete, including any remote interface panel or special-purpose
module wiring.
Automatic City Water Switchover (if included) is installed, flushed, and leak-tested.
Condenser, if applicable, is installed, piped, wired, and leak-tested.
All responsible installing contractors and sub-contractors are notified to have
representatives available on site to provide technical support for the initial start-up
procedure.
Full load shall be available for chiller on the initial start-up date.