6 MAINTENANCE
6.1 Suggested Maintenance Schedule
Operation Tools required
Execution
Period
Operator Technician
General cleaning.
A slightly moist, non-
abrasive cloth.
4 months
Visual check that all
components of the metal
detector are undamaged.
-
4 months
Visual inspection of connectors
and power supply cables.
-
4 months
Floor anchoring inspection:
ensure that the archway is
firmly anchored to the floor. *
-
4 months
Cross-bars inspection: ensure
that the cross-bar screws are
properly tightened.
Supplied Allen Key N°8
4 months
Control unit inspection: ensure
that the mounting screws are
properly tightened.
Supplied Allen Key N°5.
4 months
Verification of the visual
indicators.
-
Daily (mandatory)
At shift changes
In case of doubt of
proper operation
Operator-level functionality
test.
OFV kit or Test piece
specified by the Security
Standard in use.
Daily (mandatory)
At shift changes
In case of doubt of
proper operation
Technical-level functionality
test.
TFV&FGA kit.
6-12 months
Verification of the calibration.
Re-certification of the
calibration
Test piece specified by the
Security Standard in use.
12 months (mandatory)
Battery replacement.
Supplied Allen Key N°5
2 batteries.
Recommended: 3 years
(maximum: 5 years)
6.2 Diagnosis
Generic Messages
Display Message
Sounder
Possible cause Recommended action
FAULT
RX ERR
fault in the receiving section. Check the choice of transmission channel (function CH)
if more than one metal detector is installed (see related
para. in ‘Installation’ section).
replace the control unit .
FAULT
GATE rx
FAULT
GATE tx
x : 1, 2, …
connecting cable damaged or
disconnected.
check the connections between control unit and
antenna (GATE rx: check the RX antenna; GATE tx:
check the TX antenna).
check that no nails or screws have been driven into the
antennas without prior consultation with the technical
department
replace the connecting cable.
Damaged control unit. Replace the control unit.
Damaged antenna. Replace the antenna.
PROG
-
Loading of data via the LD or IS
commands from an
unprogrammed memory cell.
Use a pre-programmed memory cell.
WAIT
Metal detector not operative. Temporary adjustment phase following to the modification
of either the receiving or the transmitting parameters (e.g.:
channel ‘CH’): wait for normal functioning indication.
303-670-1099