If maintenance or replacement of the data center side fans is
necessary the operators must follow the next steps:
1. Remove the side panels;
Orange stiener on unit top will be used to hold the fan by the eye-
bolt/belt.
four corners;
There is a risk of the fans and panel falling down thus
causing an injury during the replacement operation.
Due to the weight of the fans (approx. 35 kg) and the
panel (up to 25 kg), two technicians are required to carry
out fan replacement.