EasyManua.ls Logo

Vision REVO - Page 97

Vision REVO
122 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
SHENZHEN CENTER POWER TECH CO., LTD
Address: Rooms 9-12, 7F, Block B, Building 7, Zone 2, Shenzhen Bay Technological and
Ecological Park, Nanshan District, Shenzhen, China
Tel: 0755-66851118 Fax: 0755-66850678 Email: sales@vision-batt.com
Green Our Earth Power Your Vision
97
Step 4: Start the cabinets. Check the self-check status of all cabinets when powered on
separately.
Step 5: When the self-check is successful, a sound will appear, and the indicator light will
turn green and keep on. Proceed to step 6.
1. If self-check fails, the indicator will keep red on. If the self-test fails, you need
to check it.
2. Is it determined that it is the cell voltage/temperature/communication
failure/CBMS parameter?
3. The alarm information can be observed on the monitor and display screen
4. Detect and repair voltage/temperature/communication faults, return to step 3
and retest in order
Step 6: Close all battery cabinets
Step 7: Cold start
Step 8: Start each battery cabinet CBMS
Step 9: Start GBMS
Step 10: Check whether the CBMS parameters are completely consistent/GBMS
parameter setting are reasonable. If it makes sense, go to the next step. If it doesn't,
recheck and make changes.
Step 11: Check the dry contacts and verify that are reasonable. If it makes sense, go to the
next step. If it doesn't, re-check and confirm the cause (Contact our technical to redefine
dry contacts)
Step 12: Check whether the communication is normal, if it makes sense, go to the next
step. If it doesn't, check the register configuration and verification and retest.
Step 13: Test the backup time

Table of Contents

Other manuals for Vision REVO