11 Maintenance
100_0201_mt_0002.fm 31
11.2 Maintenance jobs
Carry out preparations:
1. Place the machine on a level surface.
2. Decommissioning the machine.
3. Remove the rechargeable battery.
4. Let the machine cool.
11.2.1 Machine maintenance jobs
Cleaning the machine
1. After cleaning, check the cable, utility lines and hardware for loose connections, chafe marks and
other damage.
2. Immediately eliminate detected deficiencies.
Grease the ramming system – AS30e
CAUTION
Health risk from fuel, lubricants and coolants.
Do not inhale fuel, lubricants, coolants or vapors.
Avoid contact of skin or eyes with fuel, lubricants and coolants.
NOTICE
Do not use high pressure washers!
Penetrating water can damage the drive motor, electrical operator's controls or
components of the machine.
Item Designation
1 Zerk fitting
1

Table of Contents

Related product manuals