Operation CRT 36
3.5 Break-in Period
1. To break in the gearboxes, run the engine at 50% of full throttle for the first 2–4
hours. This will prevent premature wear and extend gear life.
NOTICE: Running the engine at full throttle during the break-in period could result
in premature gear failure.
2. Verify that the horizontal blade pitch links are properly assembled. When
seated on the machine, the right rotor should have an “R” designation located
towards the upper portion of the pitch link and the left rotor should have an “L”.
3.6 Before Starting
Before starting the trowel, check the following:
fuel level
oil level in the engine
condition of the air filter
condition of trowel arms and blades
Grease the trowel arms daily.
wc_gr001252

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Wacker Neuson CRT 36-25 and is the answer not in the manual?

Wacker Neuson CRT 36-25 Specifications

General IconGeneral
BrandWacker Neuson
ModelCRT 36-25
CategoryTrowels
LanguageEnglish

Related product manuals