CB Series Startup Form
Job Name:_____________________________________________________________________
Address:______________________________________________________________________
Model Number:_________________________________________________________________
______________________________________________________________________________
Serial Number:_____________________________________________
Startup Contractor:______________________________________________________________
Address:__________________________________________________
_________________________________________________________
Installing contractor should verify the following items.
1. Is there any visible shipping damage?
3. Are the unit clearances adequate for service and operation?
4. Do all access doors open freely and are the handles operational?
5. Have all shipping braces been removed?
6. Have all electrical connections been tested for tightness?
7. Does the electrical service correspond to the unit nameplate?
8. On 208/230V units, has transformer tap been checked?
9. Has overcurrent protection been installed to match the unit nameplate
requirement?
10. Have all set screws on the fans been tightened?
11. Do all fans and pumps rotate freely?
12. Is all copper tubing isolated so that it does not rub?
Ambient Dry Bulb Temperature ________°F
Ambient Wet Bulb Temperature ________°F
Refrigeration System 1 - Cooling Mode