Introduction to the manual
23
Unpack and check the units.
Check that all necessary optional modules and
equipment are present and correct.
Only intact units may be started up.
Mechanical installation (page 48)
If the drive module has been non-operational
for more than one year, the converter DC link
capacitors need to be reformed. Ask ABB for
instructions.
Check the installation site. Technical data: Ambient conditions (page 122)
Fasten the base of the cabinet to floor. Install the
drive module into the cabinet.
Mechanical installation (page 47)
Route the cables. Planning the electrical installation: Routing the
cables (page 67)
Check the insulation of the supply cable, the motor
and the motor cable and the resistor cable (if
present).
Electrical installation: Checking the insulation of
the assembly (page 77)
Connect the power cables.
Connect the control and the auxiliary control cables.
Connecting the power cables (page 79),
Connecting the control unit to the drive module
(page 85), Connecting the control cables (page
86), Resistor braking: Electrical installation
(+D150 units, page 140)
Manuals for any optional equipment
Check the installation. Installation checklist (page 95)
Commission the drive. Start-up (page 99)
Commission the brake chopper (if used). Resistor braking (page 140)
Operating of the drive: start, stop, speed control etc. Appropriate Firmware Manual
Task See