46 EasyLine EL3060 Series Commissioning Instructions
Start up the Gas Analyzer
Start up the Gas Analyzer
1 Switch on the power supply of the gas analyzer
2 The name of the gas analyzer and the number of the software version
are shown in the display while booting.
3 After the start-up phase has ended, the display switches over to the
measured value display.
Example:
4 Check the configuration of the gas analyzer and alter if necessary.
5 After the warm-up phase has ended, the gas analyzer is ready to
carry out measurements.
Duration of the warm-up phase:
Uras26: approx. 1/2 hour without thermostat, approx. 2.5 hours with
thermostat
Magnos206: approx. 2 hours
Caldos27: approx. 1/2 hour
Caldos25: 1…4 hours, depending on the measuring range
6 Check the calibration of the gas analyzer.
The gas analyzer is calibrated ex works. However, transport stresses
and the pressure and temperature conditions at the installation site
may influence the calibration.
7 Feed in the sample gas.

Table of Contents

Other manuals for ABB EasyLine EL3060 Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB EasyLine EL3060 Series and is the answer not in the manual?

ABB EasyLine EL3060 Series Specifications

General IconGeneral
BrandABB
ModelEasyLine EL3060 Series
CategoryMeasuring Instruments
LanguageEnglish

Related product manuals