Installation and commissioning guide
2750 515-1 EN, REV. 14, 2020-06-26
4.3 Preparations
4.3.1 Lifting the bushing
Overview
G005005
1 Lifting tool
30 Soft bedding, e.g. rubber mat or woodboard
31 Shackle
Procedure
1. Make sure that the crane can lift the bushing. Refer to net weight in the packing list.
2.
Loosen the M8 bolts (24).
NOTE!
It is not necessary to remove the M8
bolts.
G004684

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB GOE Series and is the answer not in the manual?

ABB GOE Series Specifications

General IconGeneral
BrandABB
ModelGOE Series
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals