Do you have a question about the ABB Galaxy Power System and is the answer not in the manual?
Efficiency | Up to 96% |
---|---|
Frequency | 50/60 Hz |
Type | Uninterruptible Power Supply (UPS) |
Topology | Double Conversion (Online) |
Parallel Capability | Yes |
Protection Level | IP20 |
Operating Temperature | 0 to 40 °C |
Cooling Method | Forced Air |
Communication Interface | Modbus, SNMP |
Dimensions | Varies by model |
Weight | Varies by model |
Lists related documents like ordering guides, drawings, and manuals for the Galaxy Power System.
General safety instructions, warnings, and compliance information for Galaxy Power Systems.
Explains hazard symbols and signal words used in the manual for user safety.
Outlines essential safety precautions for working with the equipment.
Provides specific installation notes and warnings for different regions and languages.
Lists necessary tools, hardware, and supplies for installation.
Provides specific torque values for various screw sizes used in installation.
Details site requirements and checks before unpacking and positioning equipment.
Overview of system architecture, connections, and physical considerations.
Explains suitability for Common Bonding Network (CBN) or Isolated Bonding Network (IBN).
Describes suitable installation locations and facility requirements.
Illustrates and describes a single-cabinet distributed system configuration.
Explains how multiple cabinets form larger distributed systems.
Describes how components connect to a single DC bus in centralized systems.
Details the process of installing cabinets, including mounting hardware.
Provides footprint diagrams and dimensions for 24-inch wide cabinets.
Provides footprint diagrams and dimensions for 36-inch wide cabinets.
Provides footprint diagrams and dimensions for 30-inch wide cabinets.
Step-by-step guide for cabinet installation and anchoring.
Explains procedures for grounding cabinets and system ground connections.
Specific steps for grounding the cabinet framework.
Steps for connecting the system ground to the building's principal ground point.
Illustrates various cable rack arrangements for optimal routing.
Covers special requirements for systems with more than one cabinet.
Details DC power connections to the central bus bar.
Procedures for external sense and shunt with BLJ/BIC9 bay boards.
Procedures for external sense and shunt with BIC10 bay boards.
Procedures for external sense and shunt with BIC11 bay boards.
Table detailing terminal block assignments for BIC 11.
Wiring of return circuits for BIC/controller in distribution-only cabinets.
Details inter-cabinet DC power bus connections.
Describes the procedure for connecting DC power buses between cabinets.
Covers alarm and serial bus connections between cabinets.
Procedure for connecting BLJ2/3 boards between cabinets.
Procedure for connecting BLJ2/3 to BIC10 or BIC10 to BIC10 boards.
Procedure for connecting BLJ2/3 to BIC11 or BIC11 to BIC11 boards.
Explains how to configure bay ID and shunt size settings.
Configuration steps for BLJ2/3 boards, including DIP switches.
Configuration steps for BIC10 boards, including rotary switches.
Configuration steps for BIC11 boards, including rotary switches.
Steps to configure shunt channels via the Millennium II controller web pages.
Details setting shunt size and type through the controller interface.
Reminder to review safety precautions before AC connection.
Provides NEC table for wire sizing and ampacity calculations.
Details AC input configurations for GPS 4848/100, 4830, and 4827.
Input/output voltages for 595 and 595LT rectifiers.
Input/output voltages for GP100 series rectifiers.
Input/output voltages for NE series rectifiers.
Steps and cautions for routing AC cables to the cabinet.
Illustrates how to attach AC conduit to the cabinet.
Shows rectifier positions for GPS 4848/100 dual shelf.
Shows rectifier positions for GPS 4830 with different AC feeds.
Shows rectifier positions for GPS 4827 with different AC feeds.
Cross-reference table for GPS 4848/100 AC input panels.
Detailed cross-reference table for GPS 4830 AC input panels.
Detailed cross-reference table for GPS 4827 AC input panels.
Specific wiring diagrams for ED8314230 Group 2 AC input panels.
Specific wiring diagrams for ED8314230 Group 3 AC input panels.
Specific wiring diagrams for ED8314230 Group 4A AC input panels.
Specific wiring diagrams for ED8314230 Group 7 AC input panels.
Specific wiring diagrams for ED8314230 Group 10 AC input panels.
Specific wiring diagrams for ED8314230 Group 11 AC input panels.
Specific wiring diagrams for ED8314230 Group 18 AC input panels.
Specific wiring diagrams for ED8314230 Group 20 AC input panels.
Specific wiring diagrams for ED8314230 Groups 24/25 AC input panels.
Specific wiring diagrams for ED8314230 Group 26 AC input panels.
Specific wiring diagrams for ED8314230 Group 27 AC input panels.
Illustrates wire termination for specific AC input panel groups.
Specific wiring diagrams for ED8314230 Group 28 AC input panels.
Specific wiring diagrams for ED8314230 Group 518 AC input panels.
Specific wiring diagrams for ED8314230 Groups 520/522 AC input panels.
Specific wiring diagrams for ED8314230 Group 521 AC input panels.
Procedure to modify AC panels for phase-to-neutral connections.
AC input recommendations and wiring for GPS 4827.
AC input recommendations and wiring for GPS 434.
AC input recommendations and wiring for GPS 4830.
Details bottom cable feed configurations for GPS 4848/100.
Final steps for completing the AC connection process.
Describes DC distribution panels, fuses, circuit breakers, and alarm cards.
Cross-reference table for different DC distribution panel types.
Procedures for connecting loads to the DC distribution system.
Guidelines for routing AC and DC cables for optimal performance.
Information on installing and using the Capacitor Charge Unit.
Steps for mounting large circuit breakers onto panels.
Steps for mounting small plug-in breakers and fuses.
Specific information on the ED83143-31 Group 1 distribution panel.
Specific information on the ED83143-31 Group 2 distribution panel.
Specific information on the ED83143-31 Group 5 distribution panel.
Specific information on the ED83143-31 Group 11 distribution panel.
Lugs and hardware table for ED83143-31 Group 11.
Specific information on the ED83143-31 Group 12 distribution panel.
Lugs and hardware table for ED83143-31 Group 12.
Specific information on the ED83143-31 Group 15 distribution panel.
Specific information on the ED83143-31 Group 16 distribution panel.
Lugs and hardware table for ED83143-31 Group 16.
Specific information on the ED83143-31 Group 21 distribution panel.
Specific information on the ED83143-31 Group 22 distribution panel.
Specific information on the ED83143-31 Group 53 distribution panel.
Specific information on the ED83143-31 Group 54 distribution panel.
Specific information on the ED83143-31 Group 55 distribution panel.
Specific information on the ED83143-31 Group 56 distribution panel.
Lugs and hardware table for ED83143-31 Group 56.
Specific information on the ED83143-31 Group 58 distribution panel.
Specific information on the ED83143-31 Group 71 distribution panel.
Details the Low Voltage Load Disconnect (LVLD) feature and EBV circuit pack.
Information on the EBV circuit pack for load disconnect functionality.
Introduces RPM modules for data acquisition and control.
Lists available RPM modules and their functions.
Explains the requirement and availability of current limiting resistors.
Illustrates possible mounting locations for RPM modules.
Step-by-step guide for installing RPM modules.
Procedures for connecting and disconnecting batteries.
Explains battery connection panels, shunts, and controller interaction.
Cross-reference table for various battery connection panel types.
Options for connecting more than eight battery leads.
Illustrates different battery connection panel configurations.
Procedures for connecting positive and negative battery conductors.
Step-by-step guidelines for installing battery connection panels.
Details the Contactor Control Board and its switches/LEDs.
Guidance on installing battery and alarm fuses/breakers.
Introduces the installation procedure for fascia covers.
Procedures for installing front and end-of-line fascia covers.
Explains the procedure for connecting office alarms.
Details connecting controller alarms using alarm boards.
Steps for system checkout before installing rectifiers.
Pre-installation checks for rectifier shelves.
Reminder of safety precautions during power-up procedures.
Illustrations of the Millennium II controller front panel.
Procedure for turning on the system with default firmware.
Notes regarding rectifier installation and shelf covers.
Step-by-step guide for installing the first rectifier module.
Steps to verify controller setup and operation after rectifier installation.
Procedures for setting the ID number for each rectifier.
General instructions for installing rectifier modules.
Procedure to test controller and rectifier LEDs.
Procedure to calibrate the controller's voltage display.
Steps to set the system's float voltage.
Procedure to configure shunt types and sizes.
Steps to enable and configure the LVBD feature.
Steps to enable and configure the LVLD feature.
Procedures for connecting batteries to the system.
Procedures to test rectifier performance and load sharing.
Procedure to test system alarms.
Procedure to test the BD (Battery Disconnect) alarm.
Procedure for testing system alarm relays and wiring.
Final step to connect equipment loads to the system.